History

Since its commissioning in 1896 the Mackay Port Authority has been at the forefront of development in the Mackay Region, from the wholehearted support of the tourism industry through to maintaining a first class port facility. The history of the Authority has been detailed in the Annual Reports.

Click here for Diary Events from 1947 - 1950







Annual Report - Diary of Events 1947-1950
1947
The rainfall registered at the Harbour for the twelve months ended 31st March 1947 was 2991 points.

The quantity of water sold to coastal shipping was 1,099.000 gallons.

The Opportunity was taken of hiring from the Harbours and Marine Department the dredge "Morwong" whilst on its way to Townsville, and all three berths and portion of the swinging basin were dredged. The berths are now back to their original depth of 33 feet lowest alongside the Pier and 29 feet at the Breast Wharf.

The cost of this dredging amounted to £4136

1948
The rainfall registered at the Harbour for the twelve months ended 31st March 1948 was 2371 points.

The quantity of water sold to coastal shipping was 1,270,000 gallons.

Further capping - about 350 feet - of the northern breakwater has been completed.

A lease of 20 years has been granted to the Australian National Power Alcohol Company of an area four chains square, being portion of the reserve set aside for oil installations. The rental is fixed at £2 per week for the first ten years, then to re-appraised for the remainder of the term.

1949
Quantity of water sold to ships in 1949 was 1,270,000 gallons.

The Rainfall at the Harbour for the 12 months ended 1st March 1950 was 3797 points.

A shelter shed for launch passengers was erected at the eastern end of the Breast Wharf.

Pioneer River - There appears to be no material change in the course of the river, and the channel depths have not altered. It is likely that in the near future beacons and lights for day and night traffic of tourist fishing vessels will be restored.

1950
Quantity of water sold to ships in 1950 was 1,611,000 gallons.

The Rainfall at the Harbour for the 12 months ended 1st March 1950 was 5534 points.

The principal work carried out during the period consisted of the concreting of piles at the Breast Wharf upon which £955.9.11 was expended; the overhaul of sugar conveyors, the replacement of a new refrigerator in the cafe, the building of extra lockers on the Breast Wharf and Pier for the Adelaide Steamship Company; the enlargement of the waterside workers mess room on the Pier; the building of a crane shed on the pier and other sundry jobs.

The Mackay Broadcasting Service made application to the Board for an area of land on the South East corner of Mt Bassett. This area was cleared for them with the Boards Bulldozer, and power is being connected to the area. It now only requires the underground equipment to be placed in position and this work will be finished.

A new well at the Harbour behind the Pilot Station cottages was sunk to a depth of 18 feet, but no water was found.

The Palm Avenue to the harbour is making good progress. Palms, where necessary, have replaced those that have died.

Pine trees planted south of the Southern Breakwater are thriving though growth is slow.

Bougainvillea and Oleanders on each side of the roadway from Slade Point turnoff to the Harbour are making good progress.

Approximately 120 coconut palms were purchased from Seaforth and these have been planted in between the pines in the fenced off area at the harbour.

Annual Report - Diary of Events 1958
January
The Board decided on a beautification scheme for the Outer Harbour approaches and beaches.

February
Highest ever flood sweeps down the Pioneer River reaching a record height of 29 feet. Forgan Smith Bridge badly damaged.

March
State Government alters Harbour Board election system to provide for seven members elected by District Councilors, two members nominated by Government on all Queensland Harbour Boards.

April
Cyclone crosses coast north of Mackay on evening of April 1st. Bowen severely hit with extensive damage to Port and town.
Work commences on improving intake of Bulk Terminal to lift receiving rate to 450 tons per hour.

May
New well for Harbour water supply put down near Seamen's Mission at Outer Harbour.

June
Installation of new receiving equipment at the Bulk Sugar Terminal completed.

July
First meeting of the new Board following the Triennial elections.

A small suction dredge built by the Board was put into operation to pump sand from the Harbour to a reclaiming area north of the Bulk Terminal Storage Shed.

August
Work of restoring the moles and miniature lighthouses on the North and South Breakwaters completed, following damage sustained in the March 1956 cyclone.

September
Work commenced on raising the storage capacity of the Bulk Sugar Terminal by 20,000 tons to cope with anticipated requirements for the 1958 crop.

October
Board constructs 10 chains of flood prevention wall in the Foulden area of the Pioneer River as an emergency measure.

November
Construction of a further 35 chain of flood prevention wall in the Foulden Area commenced.

December
Emergency flood prevention wall on the north bank of the Pioneer River in the Foulden area completed.

Board decides to purchase a suction-cutter dredge of from 12-16 inch capacity for Outer Harbour and River work.

Annual Report - Diary of Events 1959
January
The Board approved in principle a proposal to erect an export cold store in the Outer Shed of No1 Pier and agreed that it would meet up to half the cost of installation.

February
A cyclone crossed the Queensland coast in the vicinity of Ayr causing extensive damage in Ayr, Home Hill and Bowen but comparatively minor damage only in Proserpine and Mackay. The Forgan Bridge over the Pioneer River was severely damaged in a flood on the 16th and was kept open for traffic by the erection of temporary Bailey bridging over the affected spans by the Royal Australian Engineers.

March
Large quantities of material and stores for the Australian Army's manoeuvres south of Mackay received at the Harbour on Army vessels "Basse" and "Tara". These vessels subsequently loaded large quantities of store for return to Army Depots on completion of the Exercises.

May
The adopted proposals to win rock from Mt Basset Quarry by tunnel blasting and driving of the first tunnel was commenced.

June
A meeting of representatives of the Irrigation and Water Supply Commission, the Mackay City, Pioneer Shire and Mirani Shire Councils, The Mackay Regional Electricity Board and the Mackay Harbour Board was held to consider the formation of a Pioneer River Trust.

July
The Pioneer River Trust was formed with representatives from the Mackay City Council and Pioneer Shire Council and the Mackay Harbour Board.

August
Construction of a small craft jetty for the use of private boat owners in the Mackay Outer Harbour was completed.
The Board adopted proposal for the leveling of 32 acres of land for industrial development in the Harbour area.

September
Visit of Her Royal Highness Princess Alexandra to Mackay on the first of September. The Princess arrived in Mackay on the destroyer HMAS "Warramunga".

Leveling and development of 32 acres of land for industrial sites at estimated cost of £30.000 commenced.

The Commonwealth Meteorological Bureau's Radar equipped weather station at Mt Bassett was completed and commenced operations.

October
The Board's plan for the reclamation of 300 acres of land at East Mackay as a flood prevention and City Development measure was accepted in principle at a meeting of interested Local Authorities.

November
The Board approved proposals to erect a jetty/wharf in the outer harbour for the development of the Tourist Islands cargo trade.

December
The Port received a Centenary year visit from a destroyer of the British Navy, HMS "Solebay".

Annual Report - Diary of Events 1960
January
Completion of new bore for improvement to water supply in Harbour area yielding 8000gph on test

Euclid twin power scraper of 24 cubic yard capacity arrives to commence reclamation work for development of the Board's Industrial Estates at the Outer Harbour.

February
Construction commenced of the new Cafe at the Outer Harbour and also of an amenities block at the popular Harbour Beach.

March
Construction commenced of the new Fishermen's Wharf in the Pioneer River to replace the old timber "Queens" wharf for use by the professional fishermen operating from Mackay.

May
Board approves plans for construction of road north from the harbour to Lamberts Beach.

June
Board staff assists with searches and salvage work following crash of Fokker Friendship Abel Tasman off Hay Point on the 10th June. The memorial to those lost in in he crash was unveiled at Far Beach on the 26th June.

The Vacuum Oil Company commenced construction of an Ocean Oil Terminal estimated to cost £100,000 making the third terminal at the Outer Harbour.

July
Land reclamation by the Euclid Twin Power 24 cubic yard scraper for industrial sites near the Outer Harbour completed.

August
New Harbour Cafe completed and officially opened on the 18th August.

September
Sheeting of reclaimed area for industrial leases south of Harbour Road completed.

Board approves formation of a Volunteer Fire Brigade at Outer Harbour.
The Harbours and Marine Dredge "Morwong" arrives from Brisbane to restore depths in swinging basin and berths in the Outer Harbour.

December
Dredge "Morwong" returns to Brisbane for three months after completing about 50% of its work in Mackay.

Annual Report - Diary of Events 1961
January
The Board's old steam shovel was converted to a heavy lift electric crane and erected on the south berth of No 1 pier.

Construction of the Island Trade Wharf commenced.

February
Construction of bitumen roads to the south side industrial area and north breakwater and provision of water supply to south side industrial area commenced.

March
Development road north from Harbour along Lamberts Beach constructed.

The old "Queen's" or Fishermen's Wharf in the Pioneer River was demolished, making way for a reinforced concrete wharf for the Fish Board.

April
Largest tanker ever to use Harbour - the "Kollbryn" 560ft length and 20,000 tons deadweight - berthed.

May
Visit of USS "Gurke" to port for two day good-will visit.

Dredging o of Harbour berths and swinging basin by "Morwong" resumed.

July
A meeting of State Cabinet was held in Mackay on July 24th, the first such meeting ever held in Mackay.

August
Commencement of construction of ACF and Shirleys' Fertilisers aqua-ammonia depot at the Harbour.

Dredging of the Outer Harbour by Harbours & Marine Dredge "Morwong" completed.

September
Visit of British Frigate HMS "St Brides Bay" on good-will visit to Mackay.

October
Burns Philp inaugurate coastal cargo service to Mackay

November
Island Trade Wharf opened for traffic
Messrs. ACF & Shirleys Fertilisers bulk aqua-ammonia depot at the Outer Harbour completed

December
Queensland Harbour Boards' Association Conference held in Mackay December 6th-8th.

Construction commenced of Mackay Surf Life Savers' Club house at the Harbour Beach.

Annual Report - Diary of Events 1962
January
Board purchases a forty foot work boat from the Department of Supply. The boat was subsequently re-named the "A J Coyne" honouring the former member of the Board of that name.

February
Life Saving Club house opened at Harbour Beach by Mr R Camm MLA Member for Whitsunday

March
Board approved purchase of grab dredging plant at estimated cost of £55,000.00

Construction of new tourist jetty at estimated cost of £54,000.00 commenced.

April
Centenary of the Settlement of Mackay District celebrated and first edition of the Mackay Centenary Booklet issued.

First shipment of aqua-ammonia received at the Outer Harbour.

Tenders accepted for construction of 100 ton crane barge and 250 ton dumb hopper barge for dredging plant.

May
Visit of submarine USS Segundo to Port, <ay 12th to 14th for Coral Sea Week

June
HMAS "Quickmarch" and "Quiberon" made goodwill visit to Port June 1st to 4th.

Board resolved to investigate possibility of establishing small boat harbour for Mackay private boat owners in Bassett Basin

July
First discussions held with Board regarding possibility of increasing raw sugar storage at Outer Harbour.

August
New carpenters workshop at Harbour completed and occupied.

September
Consulting engineers report on proposed second shed for storage of bulk raw sugar at Outer Harbour adopted. Estimated cost of Terminal addition was £965,000

October
Construction of Bulk Sugar Terminal additions commenced, Board undertaking work on concrete foundations and substructures by day labour.

November
First concrete poured for the second bulk raw sugar storage shed on November 21st by Harbour Board employees.

December
Crane barge "James Pearce" and dump Hopper barge "Pioneer" for Board's grab-dredging plant delivered to Mackay by suppliers.

First stage of new light scheme at Outer Harbour brought into operation by switching on of lights on Southern Breakwater and on Harbour Beach.

In the six months ended December 31st 1962 374,622 tons of sugar were shipped from he Harbour 58 vessels, The previous record tonnage was in 1958-1959 when 330,346 tons were shipped in the full year.

Annual Report - Diary of Events 1963
January
The new reinforced concrete jetty for tourists, named "Loves Jetty" by the Board was opened for traffic.

February
A further 55,000 tons of rock for the strengthening of the northern and southern breakwaters brought down by tunnel blast No 11 on Mt Bassett Quarry. In all 359,000 tons of rock have added to the breakwaters between 1961 and 1963.

March
Board adopted a recommendation by the Chairman Mr J Langdon to build a tourist lookout on Reservoir Hill overlooking the Harbour and mouth of the Pioneer River.

HMAS "Quickmarch" and "Queensborough" make good-will visits to the Port.

May
Dredging of the Harbour swinging basin and berths with the Boards new grab dredging plant commenced.

The Board decides to build new offices at the Harbour and to dispose of its River Street Offices.

June
Imports and Exports for 1962/63 highest in Boards history - 84702 tons and 563291 respectively.

July
New sealed road to Reservoir Hill and the Harbour beach parking area complete.
August
The Australian National Line inaugurate a direct Melbourne-Sydney-Mackay Shipping service using 'E' Class vessels.

October
New lookout completed at Reservoir Hill

Raw Sugar received into the new second storage shed of the Bulk Sugar Terminal for the first time on 21st October.

November
The Board agrees to construct a cold store of 500 tons capacity for the export meat trade in the outer shed on the pier.

Plans announced to build a third 1000 foot sugar shed at the Mackay terminal for 1965 and to extend immediately the almost completed second shed by 150 feet to 1000 in length.

December.
A fortnightly service from Brisbane to Mackay by the Wide Bay Shipping Co Ltd MV "Sarawak" commenced.

The Board approved the establishment of installation for molasses exports and liquid petroleum gas imports at the Harbour.

Annual Report - Diary of Events 1964
January
Small boat ramp with the Harbour near the southern breakwater became available for the trailer launching of small craft.

Excavation and foundation of No. 2 Bulk sugar Storage Shed extension from 850ft to 1000ft commenced.

February
The 40ft Wooden Pile Driving Barge sank while riding at anchor on work location outside the southern breakwater on 21st February and was subsequently salvaged only to be finally damaged beyond repair while refitting.

March
Commencement of the removal of an estimated 1,235,000 cubic yards of sand from sandhills to adjoining swamplands to provide a further Bulk Sugar Terminal site of 70 acres and reclaim an industrial area of 50 acres.

April
Completion of removal of bag conveyor system and superstructure from Pier Sheds to provide clear storage space.

Commencement of site for the Bulk Molasses Terminal by widening of a section the breakwater adjacent to the Breast Wharf.

Tourist Jetty officially opened by Mr R.E.Camm MLA for Whitsunday.

June
General Cargo service from Melbourne and Sydney to Mackay taken over by the Australian Nation Line and arrival on first trip of "Boonaroo" with large palletised and containerised cargo.

ARC Engineering (QLD) PL commence construction of their re-inforcing steel fabrication and processing plant on a 3 acre lease in the Light Industrial area at the Harbour.

July
The board was re-constituted and Mr Landon was appointed Chairman and Mr Muller Deputy Chairman

First shipment of 120 tons of LP Gas arrived in the tanker "Arago" for storage in the newly established LP Gas Terminal at the Harbour tank farm and for use by the Mackay Gas Co

Completion of the No 2 Bulk Sugar Storage Shed to 1000ft and 240,000 tons storage capacity.

Completion of rubber fendering of the Pier berths and knuckles.

August
The Outer Harbour is 25 years of age on 26/8/1964

Commenced construction of 7000 ton Molasses Storage Tank

Jeff Rogers & Co commences building of a fibre glass products processing plant on 2 acres of land on the Light Industrial area at the Harbour.

September
The largest ship to enter the Harbour, the 14,782 tons gross, 22,300 tons deadweight bulk carrier "Barbara" being 566' 22" in length with a draught of 32'1 3/4" berthed on 8th September, and sailed within 23 hours with a cargo of 19,940 tons of sugar and a draught of 31' 6".

The first permanent tug arrived to take up duties in the Harbour. This is the 2 ton bollard pull tug "Bega" which is to be replaced by a 5 ton bollard pull tug with a few months.

Floor of the 600 ton net Cold Store laid ready for construction of the Cold Store to operate in the coming year for the meat export trade.

Ten vessels departed during September with 69,000 tons of cargo and eight vessels discharged 19,500 tons of cargo.

The "drop ball" system of spalling rock in the Quarry was commenced to increase production to meet rising demand.

3 LP Gas operated forklifts were acquired for working in the hold of ships as well as on the wharves.

October
Main excavation and foundation commenced for the No3 Bulk Sugar Storage Shed.

The Mackay Lumber Co commenced building a Sawmill and Mounding Factory on its 5 acre lease on the Light Industrial Area at the Harbour.

Pioneer Concrete (Qld) PL established is ready mix concrete batching plant on the 3/4 acre lease at the Harbour.

The Bulk Sugar Terminal established an intake record for one week of 27,259 tons of sugar.

Annual Report - Diary of Events 1965
Nov 1964
First Molasses received into the new 7,000 ton Molasses Terminal 30/11/64

The Readymix Group commences operation at its new stone crushing plant in the Board's Quarry.

December
First shipment of Molasses from the new Molasses Terminal, 1480 tons in the "Nichian Maru" to Sydney

Completion of the 120 acre reclamation which provided 20 acres of land for Bulk Sugar Terminal Extensions and 100 acres reserved for heavy industry.

Construction by day labour commenced on the Board's new office at the Port.

Bulk Sugar record intake of 567,338 tons of sugar.

Geophysical survey of Harbour and approaches carried out to provide information for any major dredging in the future.

Permission granted to ARC (Qld) PL to extend premises by 75 feet.

February
Cold Store of 79,200 c.ft. and 600 tons capacity for meat export trade complete a cost of (pounds) 43,000 and tested to 5 degrees F.

March
Leases in the Light Industrial area granted to the Mackay Printing & Publishing Co. 1 acre, and an extension from 5-6 acres granted to the Mackay Lumber Co.

April
New one storey office block on the Pier for the Pier master and Stevedoring companies, also incorporating separate Amenities Rooms for Harbour Board employees and Foremen Stevedores plus a canteen, completed at a cost of £15,231.00

May
Tug "Palm Beach" of 4 3/4 tons bollard pull owned and operated by Stannard Bros. Tug Co P/L commences full time operation in the Port.

New amenities block designed to accommodate 100 stevedores completed at the cost of £14,595.00.

Coral Sea commemoration visit by USN Minesweeper "Pluck", also visits by RN Submarines "Taciturn" and "Trump" and RAN Destroyer "Anzac".

Salvaging operation at sea carried out by Board's crane barge "James Pearce" on 23rd May

June
Preliminary scheme for land backed berth approved at estimated cost of £734,000.00.

Bunkering Visit by the RAN Destroyer "Anzac"

July
Extension of the Australian National Line coastal shipping service from Melbourne and Sydney from 6 weekly to 3 weekly.

Visit from Utah Development Co. in connection with their extensive coal deposits extending into the port hinterland.

Annual Report - Diary of Events 1966
Largest Sugar Ships to date...
We have been paid the signal honour of being entrusted with the largest sugar ships to date in the Australian trade. Four ships took 73,534 tons of sugar. Between August 10th and August 16th this year the Mackay installations loaded 68,000 tons of sugar in five days into five ships. Record shipment was 21,933 tons of sugar in the "Ante Topic". The longest ship was the "Cape Marina" 584' 9" overall length. The deepest draft was "Yannis" with 32' 6".

During the year the third bulk sugar store has been completed, making total bulk sugar storage at the Port 420,000 tons.

Survey Undertaken
A geophysical and drilling survey has been carried out to determine the nature of the sea bed within the harbour and for 1.6 miles outside the harbour entrance to the sx fathom contour. Although the present depth outside the harbour is downwards from 30 feet LWST at the entrance and the necessity for dredging a lead-in channel is somewhat remote, the opportunity is being taken to investigate this possibility should it arise.

Breakwater Extension
By the end of the year the Breakwater Extension will have progressed about 200 feet out to sea. This major work will provide better protection within the harbour, and will make possible prolonged entry time for shipping beyond the resent limitation of slack water. Final design of the extension which is expected to 600 feet is the subject of a model experiment being carried out by the Department of Harbours and Marine.

Hand in hand with the growth of the sugar industry at Mackay we have welcomed the growth of the bulk petroleum and the fertiliser trade and more recently the molasses trade.

Breasting Dolphins under construction
So far as the tankers are concerned we are in the process of building three breasting dolphins at the Breast Wharf to stengthen this wharf for tankers.

VHF Radio
VHF Radio is being installed for shore to ship and ship to shore communication.

Annual Report - Diary of Events 1967
New Receiving and Storage Facility
A new 13,000 ton receiving and storage facility was built for operation in August to handle the shipment of a new sugar industy export, sugar can invert.

New Water Supply
A new water supply scheme is being installed from a source capable of supplying well in excess of 10 million gallons per day to industrial users.

A four lane highway is in course of construction to the port.

Ocean Oil Terminal construction commenced
The Shell Co of Australia Ltd. has commenced construction of the Port's second major Ocean Oil Terminal. The Terminal, expected to be operational in January 1968, will handle receipt and distribution of five major oil products.

The Board investigates entry for larger vessels
The Board is keenly aware of trends in ship size and is currently investigating means of providing entry for ships of 70,000 tons capacity.

Seismic survey reveals easy dredging to a depth of 50 feet LWST, although it is unlikely that more than 7 feet of dredging would be required in the harbour entrance to permit entry of 70,000 tonners. The great factor in favour of Mackay for deep drafted vessels is proximity to deep water. It is believed that ready access can be found the the Great Barrier Reef for ships both North and South bound.

Annual Report - Diary of Events 1968

Water Supply Improvements
In keeping with its policy of providing first class facilities the Board has abandoned its own local water supply system which has serviced the Harbour since the start of construction in 1934, and is now obtaining water from Mackay City Council through the Pioneer Shire Council. The work required was the laying of two miles fo 10" and 15" dia. water main by the Pioneer Shire Council and 3/4 mile of main by the Board. Estimated cost to the Broard for this project is $100,000. The Board also spent $5,000 on the start of reticulation improvements to guarantee a deivery rate of 40 tons of water per hour to all ships.

Love's Jetty Extension
The original tourist jetty, a timber structure built in the 1950's, was dismantled and is being replaced by an extension to Love's Jetty with a fourth concrete pier. Up to nine vessels occupy this jetty at one time.

Slipway
The Board also commence during the year the construction of a slipway with a capacity to slip vessels up to 150 tons.

Breakwater Extension
The Department of Harbours and Marine are continuing at the University of Queensland the model bodies of the breakwater extension. Because of other work only 24,000 tons of rock was placed in the extension during the year bringing the extension to 250 feet out of the 600 feet projected.

Highway Construction commences
Construction of a four lane highway by the Main Roads Department from North Mackay to the commencement of the Board's land, a distance of 1 3/4 miles commenced July 1967. The first 3/4 miles was widened and bitumened and one of the two lane re-inforced concrete bridges over Vines Creek was completed by July 1968, when the second section of one mile was commenced. Total cost of the works by the Main Roads Deparment is expected to be $500,000 with completion next year.

It then remains for the Board, commencing in July 1969 to continue the road widening into its own road system. Design provides for 2,100 feet of 2/24ft carriageway with 20' median and 900 feet of 2/24ft carriageway with 4' median which, complete with kerbing and channelling, is estimated to cost $100,000, and is expected to be completed early in 1970.

Annual Report - Diary of Events 1970

Langdon Container Berth
Most significant event in port development this year was the completion and official opening by the Member for this electorate, The Hon. RE Camm, MLA, Minister for Mines and Main Roads, of the Langdon Container Berth.

Industrial Land
A further 89 acres of land was purchased during the year as the Board's overall plan for port development embraces a port and industrial estate based on Mackay Harbour of 1,000 acres. A new street, Spiller Avenue, was opened during the year with railway branch to Austral-Pacific Fertilisers Ltd.

Small Boat Harbour
A start has been made on Small Boat Harbour facilities with the commencement of the dredging contract. There is provision being made for 100 vessels.

Queens Visit
Her Majesty Queen Elizabeth visited Australia for the Captain Cook Commemoration celebrations, and Her Majesty boarded a launch in Mackay Harbour on 16th April prior to boarding HMY "Britannia"..

Annual Report - Diary of Events 1971

Tourism
Mackay continues to foster a flourishing Tourism industry.
The Harbour continues to be the most visited tourist attraction.
Bulk Sugar Terminal inspection twice daily are always popular as is the Harbour Beach and John Mulherin Park.
Tourist Jetty berthings by commercial Barrier Reef and Island cruise and supply vessels were greater than last year, 1,017 berthings being made.

Small Boat Harbour
The Department of Harbours & Marine has advised that with dredging of the Small Boat Harbour completed, the extension of the boat ramp and the construction of 60 moorings is being programmed for 1971-72.
This is the limit of the Small Boat Harbour capacity and we will be advising the Department to plan for a larger Small Boat Harbour outside the restricted area available in the Mackay Harbour.

Annual Report - Diary of Events 1972

Modern Port Concept
In considering the successful development of a modern port the Board believes it is essential the port provides safe access and berthage for vessels of 50,000 to 100,000 deadweight tonnage if the port's operational costs are to keep pace with current economic trends.

The port must have adequate support facilites such as a highly developed infrastructure, and an adequacy of suitable land resources.

Finally no harbour can be developed with detriment to the environment.

Annual Report - Diary of Events 1973

Mackay Harbours Large Ship Potential
The Board was very keen to implement its Northern Harbour Extension Scheme for 100/150,000 tonnes deadweight ships, itiitally for the coal trade and subsequently for large ships in other trades in the future.

Mackay as Supply Port
Mackay Harbour is supplying the pertoleum and magnetit requirements for the coal industry and with a transport corridor to handle heavy traffic, both road and rail, the Port will be able to service industry at Hay Point and elsewhere in the Mackay Region. By forward planning, the Board proposes to keep all trade and industry options under close surveillance in what it sees as its role as Port Authority for the District.

Small Boat Harbour
The Tourist Industry's needs are for a further Small Boat Harbour and three sites have been considered by the Board's consultants - Mackay; Hay Point; and Campwyn. The Board is advised that a small boat harbour to accommodate upwards of 150 vessels would cost in excess of $1 million. The Board is attraced to a Small Boat Harbour at Campwyn; also in the Pioneer River as planned by the Mackay City Council; as part of the combined dredging reclamation at East Mackay for tourist high rise Residential A development.

Land Use Study

A Land Use Study has been carried out for Mackay Harbour lands and a strategic plan prepared embracing 530 hectares (1,300 acres) of port and industrial sites completely serviced for road, rail, water, drainage, sewerage and beautification including nature reserves for screening purposes.

Port Based Industry
Harbour Boards have been urged to keep their land for substantial port users. The Board's planning clearly confirms the relevance of this policy.

Annual Report - Diary of Events 1974

1973-74 has been a singularly busy year at the Port.

Trade
At 995,851 tonnes, trade remains around the now 1 millioon tonne record level set in 1971-72. 1974-75 however will most certainly see a new record set.

Shipping
This trade level is very comfortably handled without queuing problems and the Board continues to seek new trade.

Dredging development was carried out to improve the turnaround time on vessels.

Planning
The Board is keenly aware of the need to plan for the future.

The study carried out by Consulting Engineers (Messrs. Ulman & Nolan) has proved invaluable in framing forward policy. The report entitled "Mackay Region Port Requirements to 1990" highlights the need for certain initiatives which are being taken by the Board with the cooperation of the appropriate agencies. The Board is working closley with the Pioneer Shire Council as regards zoning, strategic planning and environmental considerations.